5b/6a Task 1 Project Management (milestone)

  • Oregon DOT is planning to multiprocess populationsim and add seed sharing for their statewide model and contribute the improvement
    • Stefan reminded the team to say multiprocessing instead of multithreading and shared a link
    • The statewide model runs multiple years into the future and runs for 50 to 60 PUMAs
    • Plan to multiprocess by PUMA
    • MetCouncil used seed sharing to add additional nearby PUMS samples to rural areas with not enough records in small markets
    • What's the process for rogue contributions like this? How do they align with our roadmap and the managing contributions section of the Strategic Plan?
    • These contributions sound good and are from trusted sources
    • How do we decide how to share seeds - for now just used neighboring PUMAs
    • Folks interested in the project should reach out to Alex
    • Let's use this as a test case for a more formal review process
  • Discuss a few ActivitySim happenings - support for international users, commercial users, and potential new members

5b Task 2 Strategic Planning (milestone)

  • Joe working on revisions

5b Task 10 Support for Three Zone Systems and TVPB (milestone)

  • For the full scale Marin TM2 example, I corrected the drive transit issue and have traced a couple ODs to check results
  • Added ability to re-trace tap-tap calcs when pre-computed
  • I'm working through the set of review summaries we discussed
  • Jeff added a new submodel step - initialize_los - that pre-computes the tap-to-tap data
  • He's working on the shared memory data structures/access revisions for multiprocessing now
  • In response to Stefan's question last week, I drafted a DaySim PNR lot choice with ActivitySim page for discussion

6a Task 2 Complete Estimation Mode (milestone)

  • Newman drafted the non-mandatory tour frequency interaction_simulate larch notebook
  • Newman working on wrapping it with a run_all_steps feature and also revising how the 8 EDBs by person type should be merged into 1 EDB like the other submodels

6a Task 3 Telecommute Model in Cooperation with SEMCOG (milestone)

6a Task 8 Maintenance and Support (milestone)