Project Meeting 2025.01.21

Sijia Wang edited this page Jan 21, 2025 · 6 revisions

Agenda

  • Phase 9B Telecommute Status Pivot
  • Phase 10A Scoping Recap
  • Phase 9A Support Budget Cleanup Tasks (RSG) + SANDAG Example Sharrow

Administrative

  • Phase 9B Telecommute Status Pivot
    • There is a huge level of support for proposed approach.
    • RSG can implement the PSRC version without too much effort, if desired
    • WSP is amenable to implement the Consortium member's preferred solution
    • RSG to present on PSRC work at future meeting
  • Phase 10A Scoping Recap
    • Econometric Simulation task
      • Someone from each of the teams needs to bless the Scope and budget.
    • Phase 9A Support Budget Cleanup Tasks (RSG) + SANDAG Example Sharrow
      • GitHub issue 904 - why SEMCOG model takes longer using ActivitySim v1.3 (without sharrow) than v1.2
      • GitHub issue 847 - make the mode choice logsum an optional calculation in destination choice models
        • About 8 hours of effort
      • GitHub issue 820 - Fix the shadow pricing bug that sometimes allows zones to reopen in subsequent iterations
      • GitHub issue 690 - Add the ActivitySim version to the log file
      • GitHub issue 633 - Solve the duplicate column names issue in parking location choice
      • RSG remaining 9A budget covers addressing these issues
      • Also need to address the SANDAG Sharrow issues
      • There is also code review efforts that need to be completed
        • WSP has budget to do code review; WSP should assume they will do estimation code review
        • RSG should have budget available as well, but will confirm
    • Based on need for discussion of Econometric Simulation scope we will meet on Thursday, otherwise it will be cancelled