Project Meeting 2025.01.21
Sijia Wang edited this page Jan 21, 2025
·
6 revisions
- Phase 9B Telecommute Status Pivot
- Phase 10A Scoping Recap
- Phase 9A Support Budget Cleanup Tasks (RSG) + SANDAG Example Sharrow
- Phase 9B Telecommute Status Pivot
- There is a huge level of support for proposed approach.
- RSG can implement the PSRC version without too much effort, if desired
- WSP is amenable to implement the Consortium member's preferred solution
- RSG to present on PSRC work at future meeting
- Phase 10A Scoping Recap
- Econometric Simulation task
- Someone from each of the teams needs to bless the Scope and budget.
- Phase 9A Support Budget Cleanup Tasks (RSG) + SANDAG Example Sharrow
- GitHub issue 904 - why SEMCOG model takes longer using ActivitySim v1.3 (without sharrow) than v1.2
- GitHub issue 847 - make the mode choice logsum an optional calculation in destination choice models
- About 8 hours of effort
- GitHub issue 820 - Fix the shadow pricing bug that sometimes allows zones to reopen in subsequent iterations
- GitHub issue 690 - Add the ActivitySim version to the log file
- GitHub issue 633 - Solve the duplicate column names issue in parking location choice
- RSG remaining 9A budget covers addressing these issues
- Also need to address the SANDAG Sharrow issues
- There is also code review efforts that need to be completed
- WSP has budget to do code review; WSP should assume they will do estimation code review
- RSG should have budget available as well, but will confirm
- Based on need for discussion of Econometric Simulation scope we will meet on Thursday, otherwise it will be cancelled
- Econometric Simulation task