Heather Turner edited this page May 9, 2022 · 1 revision

Tentative schedule, actual dates/times TBD.

5 meetings between steering committee and writing team. There are two milestones at 40% and 60% of the project, so these meetings mark the start, mid-point and end of each phase.

Writing team to meet regularly in between to check progress

  • Kickoff Phase 1, May 16
    • progress sync 1, May 30
    • progress sync 2, June 13
  • Mid-Phase 1, June 27 2022
    • progress sync 3, July 13
  • Delivery Phase 1 + Kickoff Phase 2, July 29
    • progress sync 4, August 15
    • progress sync 5, August 29
    • progress sync 6, September 12
  • Mid-Phase 2, September 26
    • progress sync 7, October 10
    • progress sync 8, October 24
    • progress sync 9, November 7
  • Delivery Phase 2, November 15

November 15 - November 30: organization administrators prepare and submit case study.