Our Objectives:

  • Provide Customers (WP3 and WP4) with what they need
  • Use our (WP7) resources as effectively as possible
  • Fulfill our obligations according to Project Proposal

Obligations from DoW

T7.2

  • D7.2: Report on all aspects of secondary tooling.
    • O7.2.1:Evaluation of supporting tools and methods
    • O7.2.2:Decision on the supporting tools choice(s)
    • O7.2.3 Model Transformation Strategy
    • O7.2.4 Code Generation Strategy
    • O7.2.5 Requirement management tool choices
    • O7.2.6 V&V tool choice
    • O7.2.7 Test automation tool choice with experience report
    • O7.2.8 Safety analyses tools choices

T7.3

  • D7.3 Tool Chain Qualification Process Description (review will start Friday, waiting for information from Stefan R.)
  • O7.3.1 Tool chain development plan (or equivalent) (done)
  • O7.3.2 Specification of tool interoperability mechanisms (not needed)
  • O7.3.4 Specification of primary and support toolchain architecture and its embedding into the platform (diagram, ongoing)
  • O7.3.5 Infrastructure evolution strategy (due to EMF a non-issue)
  • O7.3.7 Tool chain qualification test suite (not done)

Other Issues / Activities (in particular with respect to WP3 and WP4)

  • Data Dictionary
  • Traceability
  • Documentation
    • User Documentation
    • Developer Documentation
      • O7.3.2 Specification of tool interoperability mechanisms (not needed)
      • O7.3.3 Guideline for developing the tool chain according to CELENEC (part of toolchain development plan)
    • Process Documentation
  • Versioning
  • Usability
  • Architecture
  • Testing / Test Lab / Qualification Process (Uwe)
  • LAAS to look at Qualification
  • CEA has two groups: Papyrus and Frama-C, maybe the latter can help, too?

Decision

  • D7.2 will be delivered before itea review in June, Marielle can get it ready starting April. The decisions on the various outputs will be included.
  • Last reminder to contribute to D7.2 by Sunday.
  • For specific documentation tasks, talk to David
  • Marielle on vacation: Tue until end of week
  • Cecille on vacation: Monday next week, for two weeks.
    • Michael will cover first week of Cecille's vacation
    • Marielle will cover the second week.