Project Meeting 2020.07.24

Ben Stabler edited this page Jul 24, 2020 · 14 revisions

Task 1 Project Management (milestone)

  • Revised the structure of this wiki based on Alex's comments
    • I made a couple updates based on the meeting comments so it is now ready for review
    • Keep Governance page as is for now and review/revise when we setup the website
  • Phase 6a scope being processed by AMPO
  • Updating docs for #325
    • Planning to finish next week for team review
    • Will focus on documentation for two and three zone systems after that, while Jeff works on three zones / TVPB
  • SEMCOG team (Joel and others) invited for a later meeting
  • Meeting being moved to Thursdays at 9 am
  • Concern that the Phase 5b scope is behind schedule
    • Let's keep the pressure on for end of August
    • It may slip a bit, but we can work into September and will make sure to incorporate feedback during that time as well
    • Next week let's inventory the Phase 5b work for completion

Task 2 Strategic Planning (milestone)

  • Draft strategic development and contribution plan here for review and discussion
  • Team review next week and let's plan to discuss on next call

Task 3 Two Zones (milestone)

  • Need to work on documentation

Task 10 Support for Three Zone Systems and TVPB (milestone)

  • No work this week
  • We discussed how to develop a more useful example for testing
    • The current idea is to run activitysim up to tour mode choice
    • Then