This page is meant to describe how to adjust iterations on Beta Projects, which we are using to keep track of sprints. Since changes to sprints may be necessary, I made this page. 1

  1. Navigate to Beta Projects, click on the 3 dots in the top right and go to Settings 1
  2. Go to the options for the field with the date ranges that you want to change (in this case, Sprint) 1
  3. Clicking on a date range will open up a box where you can adjust the date range for a certain iteration (sprint). Click the first and last dates to set a date range. Also, clicking "add iteration" in the bottom left will create another iteration if additional sprints are necessary.