[3653] Add documentation for Gantt
Browse files Browse the repository at this point in the history
Bug: #3653
Signed-off-by: Laurent Fasani <laurent.fasani@obeo.fr>
Signed-off-by: Florian ROUËNÉ <florian.rouene@obeosoft.com>
  • Loading branch information
lfasani authored and frouene committed Jun 20, 2024
1 parent 6b7efa3 commit 8138cc0
Show file tree
Hide file tree
Showing 19 changed files with 237 additions and 0 deletions.
2 changes: 2 additions & 0 deletions CHANGELOG.adoc
Original file line number Diff line number Diff line change
Expand Up @@ -5,6 +5,7 @@
=== Shapes

- Add support for text alignment on labels
- Add support for gantt representation

=== Architectural decision records

Expand Down Expand Up @@ -102,6 +103,7 @@ image:doc/screenshots/insideLabelPositions.png[Inside label positions, 70%]
- https://github.com/eclipse-sirius/sirius-web/issues/3606[#3606] [test] Improve error handling in ExecuteEditingContextFunctionRunner and ExecuteEditingContextFunctionEventHandler
- https://github.com/eclipse-sirius/sirius-web/issues/3561[#3561] [diagram] Add support for background and border on diagram labels
- https://github.com/eclipse-sirius/sirius-web/issues/3604[#3604] [diagram] Make node overlap resolution faster during "Arrange All"
- https://github.com/eclipse-sirius/sirius-web/issues/3653[#3653] [gantt] Add documentation for gantt representation

== v2024.5.0

Expand Down
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/specifier/images/gantt-overview.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/specifier/images/gantt-task-handlers.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/specifier/images/gantt-task-relation-tool.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/specifier/images/gantt-task-tools.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/specifier/images/gantt-tools.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
127 changes: 127 additions & 0 deletions doc/specifier/representation-gantt.adoc
Original file line number Diff line number Diff line change
@@ -0,0 +1,127 @@
# Gantt representation description

This chapter explains how to configure a `Gantt` representation in the `View` model.

A `Gantt` representation is made of a hierarchy tasks.

* A task can contain sub-tasks.
* A task can be linked to another task with a dependency relation.
Each `Task` is associated with a semantic element that is an object of the model.

image::images/gantt-overview.png[Gantt representation overview]

## Gantt description

To define how your model is represented with a `Gantt` representation, the specifier needs to create a `GanttDescription` in the `View` model.

image::images/gantt-description-overview.png[Gantt description overview]

* `Name`: A name that helps the specifier to know what the GanttDescription is about
* `Domain Type`: Type of the object on which it is possible to create the representation
* `Precondition Expression`: An expression that determines if it is possible to create the representation
** `self` variable is the semantic element associated with the `Gantt`.
* `Title Expression`: The initial name of the representation once created
** `self` variable is the semantic element associated with the `Gantt`.
* `Date Rounding Expression`: An expression that returns a string that is a time duration that will define how the date is rounded when changing the date from the Gantt representation.
The string contains
** an integer which is the number of time unit.
** a character among {D,H,m} corresponding to a Day, Hour or minute time unit.
Example: to round to half a day, the expression must returns `12H`
## Task description

The `TaskDescription` is used to define the direct tasks of its parent in the tasks hierarchy.
It can be the root tasks in the Gantt or the sub-tasks in a task.

* `Name`: A name that helps the specifier to know what the TaskDescription is about
* `Semantic Candidates Expression`: An expression that returns one or more semantic elements.
Each semantic element will be represented by a task.
** `self` variable is the semantic element associated with the `Gantt`.
* `Domain Type`: Type of the object used to filter the semantic object represented by a task
All the following expressions are called as many times as the number of semantic elements returned by the `Semantic Candidates Expression`.
`self` variable is the current semantic element.

* `Name Expression`: An expression that defines the name of the task
* `Description Expression`: An expression that defines the description of the task
* `Start Time Expression`: An expression that returns a `java.time.Instant` to define the start date of the task.
* `End Time Expression`: An expression that returns a `java.time.Instant` to define the end date of the task.
* `Progress Expression`: An expression that returns an integer between 0 and 100 to define the percentage progress of the task.
* `Compute Start End Dynamically Expression`: An expression that returns a boolean.
If true and if the task contains sub-tasks, the start and end dates displayed in the Gantt are computed from the sub-tasks.
The start date(respectively the end date) is the lower(respectively upper) date of the sub-tasks dates.
* `Task Dependencies Expression`: An expression that returns a list of semantic elements to define dependency relations between the current task and the tasks associated the returned semantic elements.
### Task description as sub task

To define tasks as the second level of the tasks hierarchy, create a `TaskDescription` in the `TaskDescription`.

It is also possible to reuse `TaskDescription` so that it is possible to define a recursive definition.
Use `Reused Task Element Descriptions` field to select existing `TaskDescription`.

## Tools

Many tools can be configured for `Task`.
All the tools are created under `GanttDescription`.
Note that, by default, a tool does nothing.
You need to add operations in the tool to make changes in the semantic model.
Typical operations:

* `Change Context`: It allows to change the `self` value.
But typically this operation is useful if you just want to call a java service that will implement the tool behavior.
* `Create Instance`: Creates a semantic object and add it in the defined feature of the `self` semantic element
* `Set Value`: Sets the value on a given feature on `self` semantic element
* `Delete Element`
* etc
Each tool gives access to variables that can be used in the expression of the tools.
When the tool is executed, the system will set the variables(that depends on the execution context of the tool) and executes the operations associated with the tool.

image::images/gantt-tools.png[Gantt tools]

### Task tools

* `Create Task Tool`: This tool defines the behavior when the user creates a task using the button in the task contextual palette in Gantt.
Available variables:
** `self`: The semantic element associated with the selected Task
* `Delete Task Tool`: This tool defines the behavior when the user deletes a task using the button in the task contextual palette in Gantt.
Available variables:
** `self`: The semantic element associated with the selected Task
image::images/gantt-task-tools.png[Task palette tools]


* `Edit Task Tool`: This tool defines the behavior when the user uses the handles to change start or end dates or the progress.
Available variables:
** `self`: The semantic element associated with the selected task.
** `newName`: The new value of the name.
** `newStartTime`: The new value of the start time.
** `newEndTime`: The new value of the end time.
** `newDescription`: The new value of the description.
** `newProgress`: The new value of the progress.
image::images/gantt-task-handlers.png[Task handlers]


* `Drop Task Tool`:
This tool defines the behavior when dragging and dropping, in the table part of Gantt, a task before, after or inside another task.
Available variables:
** `sourceObject`: The semantic element associated with the dragged task
** `targetObject`: The semantic element associated with the target task where the task is dropped.
** `sourceTask`: The dragged `Task`.
** `targetTaskOrGantt`: The target where the task is dropped.
It can be `Gantt` or another `Task`.
** `indexInTarget`: The index of the dropped task inside the new list of tasks where it is dropped.
index=0 means first position.
### Dependency tools

* `Create Task Dependency Tool`:
This tool defines the behavior when creating a task dependency by dragging the dependency handler from one task to another.
Available variables:
** `sourceObject`: The semantic element associated with the task from which the dependency link is initiated.
** `targetObject`: The semantic element associated with the target task where the dependency finishes.
image::images/gantt-task-relation-tool.png[Create Task Dependency Tool]

Binary file added doc/user/images/gantt-overview.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task-dependencies.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task-dependency-tool.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task-dependency.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task-dragdrop.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task-group.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task-handlers.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task-milestone.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-task.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
Binary file added doc/user/images/gantt-toolbar.png
Loading
Sorry, something went wrong. Reload?
Sorry, we cannot display this file.
Sorry, this file is invalid so it cannot be displayed.
108 changes: 108 additions & 0 deletions doc/user/representation-gantt.adoc
Original file line number Diff line number Diff line change
@@ -0,0 +1,108 @@
# Gantt representation

A `Gantt` representation is made of a hierarchy tasks.
Each task can contain sub-tasks.

The left part is a table.
Each row represents a task.
The columns of the table provide information about the task.

The right part is the Gantt itself.
Each row displays a task.
A task can be linked to another task with an arrow to represent a dependency relation.

image::images/gantt-overview.png[Gantt representation overview]

## Gantt display

There are 3 types of task:

* The basic task
image::images/gantt-task.png[Gantt task]
A color shows the progress value of the task.
Fully colored mean 100%.

* The group task that is a task which contains sub-tasks
image::images/gantt-task-group.png[Gantt group]
A color shows the progress value of the task in the bottom part.
Depending on how the `TaskDescription` is configured in the `View` model, the task group may be either *computed from its sub-tasks* or defined independently as a basic task.
In the former case, the start(respectively end) date is the minimal start(respectively maximal end) date of the sub-tasks and the progress is a weighted average of the sub-tasks progress.

* The milestone represents a date.
image::images/gantt-task-milestone.png[Gantt milestone]

A task can have a list of dependencies to other tasks.
The dependencies are represented by an arrow between two tasks oriented from the dependency to the dependant task.

image:images/gantt-task-dependencies.png[Task Dependencies]

## Gantt Toolbar

image::images/gantt-toolbar.png[Gantt Toolbar]

* `Toggle full screen mode`: It allows to display the representation in full screen
* `Zoom level`: Choose the time unit in the Gantt (Hour, Half Day, Day, Two Days, Week, Month, Year)
* `Zoom in`
* `Zoom out`
* `Fit to screen`: Set the zoom level that allows to display all the tasks
* `Display columns`: Allow to hide all the columns in a click.
Using the drop down combo, the user chooses the displayed columns.
The displayed columns are persisted in the Gantt representation.
* `Share`: Provide an URL that reaches directly the current Gantt representation
## Selection

When selecting a `Task` in Gantt or in the Table, the associated semantic element is selected in the `Explorer` and its properties are displayed in `Details`.

## Edition

### Task attributes

Using handlers on the task, it is possible to change the start/end dates and the progress.
Clicking on the task and moving it left or right, allows to shift the date keeping the same duration.

image:images/gantt-task-handlers.png[Show/Hide Cards]

When changing a date, the date is rounded accordingly to the `Date Rounding Expression` define in the `GanttDescription`.
Holiday is set as Saturday and Sunday. If the rounded date is part of the holiday, it is moved to the next or previous working date.
Note that a date rounded greater than two days is not adjusted to the working days.

### Task dependency relation

Using the round handler next the task allows to create a dependency relation.

image:images/gantt-task-dependency-tool.png[Task Dependency Tool]
image:images/gantt-task-dependency.png[Task Dependency]


### Task reordering

From the table, it is possible to drag and drop a Task to reorder the task or change its container.

image:images/gantt-task-dragdrop.png[Task Drag and Drop]

* To reorder, drop the task before or after another.
* To change its container, drop the task on another task.
Note that it is not possible to drop a task in its own children hierarchy.


## Table

The table is made of rows and columns.
There is one row per task.

The first column presents the hierarchy of tasks.
It shows the name of the task and optionally an icon to expand/collapse the sub-tasks.
The *expand status is persisted* in the Gantt representation.

The other columns display the start/end dates and the progress.

The columns can be resized and *the column width is persisted* in the Gantt representation.
From the Gantt toolbar, the columns can be hidden (See 'Gantt toolbar' section).