Hello! Kind of new here trying to get a grasp of AB so apologies if it is a very fundamental question. |
Beta Was this translation helpful? Give feedback.
Replies: 3 comments 1 reply
-
Hi Ketan, This is exactly the right place to ask! What you're asking for (the first tier contributors) is not yet available in AB, however, we will have this in the next minor release (2.11), you can subscribe to #810 to receive a notification when this feature becomes available and you can follow progress on us building it in #1046 if you're interested. Of course, that is not useful for you right now. For now you unfortunately will have to manually record all numbers from the Sankey and make your own graphs. Do also check out our wiki page on contribution analysis to learn more about what you can and cannot do in AB. |
Beta Was this translation helpful? Give feedback.
-
Hi Marc, Thanks for the prompt response. Really interesting to see the progress and development of this overtime. Due to being quite new to this maybe it is a bit early for me to start contributing but I will try my best to support the progress. |
Beta Was this translation helpful? Give feedback.
-
@ketanvaidya |
Beta Was this translation helpful? Give feedback.
@ketanvaidya
This is now possible with First Tier contributions, which is available since Activity Browser