Notifications
You must be signed in to change notification settings - Fork 0
Other Documentation
The Project Iteration and the Progress of the project have been maintained on a Google Doc that was shared among team members. Here is the link to check it out: Progress Report
All of our team meetings have been planned through the use of the communication tool Slack and all the meetings have also been documented and maintained on a Google Doc. Here is the link: Meeting Log
The Work Plan document indicated which requirement was addressed, and for which deliverable, as well as indicated the effort (hours) put in to accomplishing the task. Here is the link: Work Plan
Below are the hours that each of us put into this project, separated by each deliverable. Each deliverable spanned approximately 1.5 to 2 weeks.
Deliverable 1 | Deliverable 2 | Deliverable 3 | Deliverable 4 | Deliverable 5 | Deliverable 6 | |
---|---|---|---|---|---|---|
Marine Huynh | 6 | 18 | 20 | 20 | 14 | 35 |
Erion Hysa | 6 | 15 | 19 | 13 | 13 | 22 |
Iliana Katinakis | 6 | 19 | 20 | 13 | 12 | 21 |
Anthony Laye | 6 | 15.5 | 19 | 15 | 12 | 40 |
Wenzong Xia | 6 | 14 | 18 | 16 | 18 | 39 |
Total per Deliverable | 30 | 81.5 | 96 | 77 | 69 | 157 |
Requirements Document
Architecture & Design Specification
Quality Assurance
Release Pipeline