Migration Plan

Problems / Priorities

There are 2 major problems in the current architecture:

  • There are complaints from call center operators that the system is not always available for ticket entry -> Availability
  • It’s hard to make a change on the existing solution, it takes long and something else usually breaks -> Maintainability

Above-mentioned problems are typical downsides of monolithic architecture. We decided to re-engineer our architecture (adr) and to switch to service based architecture gradually in order to mitigate those problems. This way, we’ll make sure changes don’t affect other parts of the system. Moreover, we’ll define priorities for service availabilities and we’ll deliver high availability for customer facing applications.

Guidelines / Principals

During re-engineering of the system, we considered;

  • prioritizing the resolution of the problems which give bad experience to the customers right now
  • these suggestions to split existing structure into smaller parts
  • Having small/measurable steps and delivering ready components

Migration steps:

  • Step #1 Start migration with problematic and decoupled entities
    • Motivation
      • We suspect the analytics module for the availability issues; running heavy queries on production database may cause load and performance degradation
      • Also, it’s easiest to migrate decoupled entities which are not customer facing.
      • For these purposes, we decided to migrate analytics and knowledge base (KB) modules
    • Expected result
      • We plan to have 2 separate new components; analytics and KB. Since analytics will have a separate database, production system load will severely reduce and customer experience will be better
    • How to achieve step #1
      • As part of analytics adr and KB adr, new databases will be created for new integrations
      • Existing monolith service will replicate analytics and KB related data to new databases
      • We will take a snapshot of needed previous analytics and KB data from existing database and will store in the new databases (we will use an extract-transform-load (ETL) tool for this purpose)
      • Analytics and KB will be served through new integrations with required changes on current system
      • We will decommission analytics and KB functionalities of monolith service

alt text Figure - migration plan step #1

  • Step #2 Migrate less dependant components
    • Motivation
      • Less dependant components - which are called but don’t give call - (e.g. notification service) are easier to migrate rather than core components (e.g. ticket workflow engine) - which have many touchpoints. Migration of less dependent components doesn’t require making a connection back to the monolith.
      • We decided to migrate these less dependent components at this step: notification service, survey manager, payment service
    • Expected result
      • Load and complexity in the monolith will reduce even more
      • Services that core components need will be ready in the new setup
    • How to achieve step #2
      • Once new notification service, survey manager and payment service integrations are done -we plan to place 3rd party softwares, needs adr-, required changes will be made in existing service separating/abstracting these modules from main structure
      • New databases will be ready for new 3rd party applications
      • If we need to keep old data for a while (for compliance/reporting etc. reasons), we need to take a snapshot of existing data (using an ETL tool) and store them in the new databases
      • We make changes on monolith service to use separated components one by one - we prefer small/measurable steps - first, use new notification service, if it works as expected, decommission old notification codes/data/usage in the monolith - repeat for other components
      • We keep old code and data for a while until we make sure a successful and smooth transition - we always need a fallback plan - we can go back to previous state if needed

alt text Figure - migration plan step #2

  • Step #3 Decouple vertical components
    • Motivation
      • Due to the fact that changes break somewhere else in current structure, we decided service based architecture and we decouple relevant services and data as much as we can (vertical decoupling)
      • We decided to separate out admin/manager profile service along with its data and reference data service on this step
    • Expected result
      • Load and complexity in the monolith will reduce even more
      • We will experience our own code in the new setup before the migration of other heavy components
      • We will introduce maintainable components
    • How to achieve step #3
      • Extract or rewrite existing code pieces, build new services based on them
      • Like in the previous steps, we copy needed data into the new databases
      • We make changes in the monolith in a way that it uses extracted vertical components
      • We decommission these functionalities from the monolith

alt text Figure - migration plan step #3

  • Step #4 Decouple the rest of capabilities
    • Motivation
      • In the final phase, we focus on existing capabilities (not code) which can be represented with a separate service
      • Capability focus will help improving our team structure and responsibilities
    • Expected result
      • We finalize the re-engineering of the system
      • We have all the components/services in the new setup
      • Monolith will be decommissioned
    • How to achieve step #4
      • We decided to separate the rest of modules into customer management system, expert management system, ticket management system, contract management system services
      • Different from step #3, here there is a possibility to lose data if we don’t plan the transition properly because these services process real-time data
      • Transition can be made at the very low traffic period (e.g. in the middle of night)
      • Old data can be copied into new databases using ETL
      • As mentioned in step #3, we prefer small steps - changes will be made capability by capability
      • We plan to introduce a replicator on top of the capability that we want to decouple - it’ll start to replicate changes in old and new services. After a successful transition, we can stop using old service for the relevant function and decommission it
        • Similar to step #2, we need to decouple less dependant capability first (Customer management service should be decoupled before contract management service since latter depends on former)

alt text Figure - migration plan step #4